Question number: 6

» Manufacturing and Industrial Engineering » Operation Research » PERT and CPM Models

Appeared in Year: 1997

MCQ▾

Question

A dummy activity is used in PERT network to describe

Choices

Choice (4) Response

a.

Resource restriction

b.

Precedence relationship

c.

Necessary time delay

d.

Resource idleness

Question number: 7

» Manufacturing and Industrial Engineering » Operation Research » Simplex and Duplex Methods

Appeared in Year: 2010

MCQ▾

Question

Simplex method of solving linear programming problem uses

Choices

Choice (4) Response

a.

Only the interior points in the feasible region

b.

All the points in the feasible region

c.

Intermediate points within the infeasible region

d.

Only the comer points of the feasible region

Question number: 8

» Manufacturing and Industrial Engineering » Operation Research » PERT and CPM Models

Appeared in Year: 2004

MCQ▾

Question

In PERT analysis a critical activity has

Choices

Choice (4) Response

a.

Zero Float

b.

Minimum cost

c.

Maximum cost

d.

Maximum Float